Expansion to the A. Grenville and William Davis Courthouse

Location:
Brampton
Project type:
Real Estate (Direct Delivery, Stipulated Sum)
Price of Contract:
$48.8 million
Ministry/Agency:
Ministry of the Attorney General

About the Project

Infrastructure Ontario was engaged on the project to construct a 110,000 square foot, six-storey addition to attach to the already existing courthouse.  Two floors will be outfitted immediately to contain new courtrooms and support spaces such as waiting areas and judicial chambers. The remaining floors will provide space for future courthouse developments.  

Project Status

  • Request for Qualifications Issued: August 16, 2016
  • Request for Proposals Issued: October 14, 2016
  • Request for Proposals Closed: December 19, 2016
  • Contract Awarded: January 13, 2017
  • Construction Start: February 2017
  • Construction Ends: March 13, 2020

Winning Bidder

Graham Construction & Engineering Inc.

Features

  • 110,000 square foot six-storey addition
  • New courtrooms and support spaces
  • Addition will include a complete basement

 

Community Features:

The expansion and improvements to the existing courthouse will help address pressures on the court system and will enhance access to justice in the community.  

 

Terms of Use

These project documents are being made available on this website for informational purposes only. Neither Infrastructure Ontario nor its clients make any representation or warranty regarding the accuracy or completeness of the content or form of these documents.

Infrastructure Ontario in its sole and absolute discretion, may choose to make available on this website amendments, revisions, modifications or replacements to these documents. These documents remain open for further revision, modification, replacement or cancellation by Infrastructure Ontario at any time and in no event shall either Infrastructure Ontario or its clients be responsible or liable, directly or indirectly, for any damage or loss caused or alleged to be caused by or in connection with the use of or reliance on the content of these documents.